Eigentümer: VERBUND Hydro Power GmbH
Betreiber: VERBUND Hydro Power GmbH
Inbetriebnahme: 1987
Typ: Laufkraftwerk
Region: Steiermark
Hauptzufluss: Mur
Leistung: 14 MW
Jahreserzeugung: 66 GWh
Turbine: 2 x Kaplan
Ausbaufallhöhe: 8 m
The run-of-river power plant was built between 1984 and 1987, consists of two Kaplan bulb turbines and generates approximately 66 GWh of electricity annually. In 2019, VERBUND started implementing digital applications for hydropower at the Rabenstein site. The power plant is a test lab for "Hydropower 4.0" – the use of digital methods and technology for the generation of electricity from hydropower.